| Schools |
Project(s) |
Progress |
| Alto Park Elementary |
Construct six new classrooms
Roof
enclose walkway to gym |
in-process
complete
complete |
| Armuchee
Elementary |
Construct two new classrooms
CCTV System
extend service road |
complete
in-process |
| Armuchee
High |
Install HVAC project Phase II
Science Lab
repair front wing of Business Education Building
renovate auditorium
renovate restrooms
paving |
in-process
in-process
complete |
| Armuchee Middle |
Construct four new classrooms
renovate science rooms
redesign HVAC for chorus and band rooms |
in-process |
| Cave Spring
Elementary |
Construct two new classrooms |
|
| College & Career Academy |
Construct a multi-purpose room with a divider |
|
| Coosa High |
Construct two new science labs
Construct a P. E. facility
renovate front of school |
complete
complete
complete |
| Coosa Middle |
Construct four new classrooms
upgrade HVAC in chorus and band rooms |
in-process |
| Floyd County Education Center |
Install new HVAC system
renovate 4 classrooms
renovate bathrooms
install fire & security system
renovate kitchen |
in-process |
| Garden Lakes Elementary |
Construct 6 new classrooms
CCTV system
roof
|
in-process
complete |
| Glenwood
Primary |
Construct two new classrooms
CCTV system
replace HVAC Units in front hall
build canopy for bus loading
install bathroom fans & heaters |
complete
in-process
in-process |
| Johnson Elementary |
Construct 4 new classrooms
CCTV system |
in-process
in-process |
| Midway
Primary |
Construct two new classrooms
CCTV system
re-work low voltage |
complete |
| McHenry
Primary |
Construct two new classrooms with restroom
Roof
battery and
attaching canopy
resurface paving in parking area
replace the gym bleachers
CCTV system
replace carpet tile in gym
install new HVAC/ERV system |
in-process
complete
in-process |
| Model
Elementary |
Construct four new classrooms
modify HVAC system
CCTV system
|
in-process
in-process
|
| Model High |
Construct new high school
construct physical education facility
install exterior lighting |
complete |
| Model Middle |
Construct four new classrooms
redesign HVAC for chorus and band rooms |
in-process |
| Pepperell Elementary |
Construct two new classrooms
CCTV system
|
in-process |
| Pepperell
High |
Renovate PE building
pave existing parking lot near creek |
in-process
complete |
| Pepperell
Middle |
Roof
Replace VCT tile in media center
resurface gym floor, ceiling, wall repaired
construct permanent walls in computer lab
modify HVAC/ERV
resurfacing and paving
CCTV system
replace tile in bathrooms |
in-process
complete
in-process
in-process
complete
complete |
| Pepperell
Primary |
Construct multi-purpose room
build canopy to the art room
CCTV system |
in-process |
| System (All Schools) |
purchase school buses
land purchases
warehouse roof replacement
lunchroom improvements and furnishings
equipment for new construction
Storage buildings
upgrade technology |
in-process
complete
in-process
in-process |